DPW Roadwork Aug 19-23

Town of Bennington Project List

Week of August 19, 2019 – August 23, 2019

 

Please be Advised: The Next Phase of PFOA Water Line extensions has begun. 

  

Harwood Hill Roadwill be reduced to One-Lane Traffic for the next several weeks for PFOA Water Line Extension Work.  Men and equipment will be on edges of the roadway.  Please use Caution and Expect Delays.

Lincoln Street Sidewalk continues to be Closed from River St to County St.  Highway crews continue sidewalks and curbing work.   Men and equipment will be in and on the edge of the roadway.  Please Use Caution when approaching this area and expect delays.

River Street – Benmont Ave to Lincoln St continues to be CLOSED to through traffic while several crews work on its rehabilitation.  Local traffic ONLY will be allowed.  Men and equipment will be in the roadway.  Please find alternate route.

Willow Roadwill be CLOSED from Duffy Dr to East Rd all week to through traffic for PFOA Water Line Extension Work.  Local traffic ONLY will be allowed.  Men and equipment will be in the roadway.  Please find alternate route.

 

TOWNWIDE:

Safety lines & Crosswalk re-paintings continue in various locations across town. PLEASE USE CAUTION when approaching these areas and expect delays

Weed eating & Roadside Mowing continues across town at various locations.  PLEASE USE CAUTION when approaching these areas and expect delays

Water Department will be repairing curb stops in various areas. PLEASE USE CAUTION when approaching these areas

Manhole Rebuilds and Road Patching across town resumes. PLEASE USE CAUTION when approaching these areas and expect delays.

 

All Work will be dependent on weather conditions.  Please use caution when entering a construction zone, men and equipment will be in the traveled portion of the road.

REMINDER:

Residents and Contractors – Please make sure ALL LOADS ARE COVERED when taking leaves and or brush to the Transfer Station.