Town of Bennington Project List

Week of July 30 – August 03, 2018

 

STATE PROJECT:  Rte 7 North-South / Rte 9 East-West: VTrans/State Highway Paving Project begins this week in Bennington.   PFOA Water Line Extensions work continues as well as Town DPW Projects and State Paving Project work.  These may require road closures or lane reductions.  Please see below.

 

Rte 67A / North Bennington Road will be reduced to One-lane traffic from Hanaford Plaza to Water Street as this section begins PFOA Water Line Extension Work.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be in the roadway.  Please use Caution and Expect Delays.

Austin Hill Road will be reduced to One-lane traffic for PFOA Water Line Extension Work (service line connections) through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edges of the roadway.  Please use Caution and Expect Delays.

Bard Road will be reduced to One-lane traffic for PFOA Water Line Extension Work (service line connections) through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edges of the roadway.  Please use Caution and Expect Delays.

Bank Street (MONDAY) will be CLOSED to through traffic from Convent Ave to Catamount Lane while Highway crews excavate, remove & replace a culvert.  Men and equipment will be in the roadway.  Please use find Alternate Route.

Bridge Street will be reduced to One-lane traffic for Paving Work through Aug 03rd, 2018.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

Cardinal Lane will be reduced to One-lane traffic for Paving Work through Aug 03rd, 2018.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

Convent Avenue (MONDAY) will be CLOSED to through traffic from Anthony Dr to Main St while Highway crews excavate, remove & replace a culvert.  Men and equipment will be in the roadway.  Please use find Alternate Route.

Fairview Street will be reduced to One-lane traffic for Paving Work through Aug 03rd, 2018.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

Gypsy Lane continues to be Closed from Rte 9/West Road to Walloomsac Road to through traffic for PFOA Water Line Extension Work through August 03rd.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be in the roadway.  Please find alternate route.

Harrington Road (North Benn) will be reduced to One Lane between the Henry Bridge and the Wastewater Plant to through traffic for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be in the roadway.  Please use Caution and Expect Delays

Heaven’s Way will be Closed to through traffic for PFOA Water Line Extension Work through Aug 03rd, 2018.  Men and equipment will be in the roadway.  Please use Caution and Expect Delays

Hillside Street (North Benn) will be reduced to One Lane for through traffic for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be in the roadway.  Please use Caution and Expect Delays

Matteson Road will be reduced to One-lane traffic from Rice Lane to Harlan Rd to through traffic for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be in the roadway.  Please use Caution and Expect Delays.

Murphy Road will be reduced to One-Lane Traffic from Austin Hill to Henry Bridge for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

Murphy Road will be reduced to One-Lane Traffic from Austin Hill to Paper Mill Bridge for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

North Bennington Road/ Rte 67A will be reduced to One-lane traffic from Hanaford Plaza to Water Street as this section begins PFOA Water Line Extension Work.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be in the roadway.  Please use Caution and Expect Delays.

Park Street (North Bennington) will be reduced to One-Lane Traffic for PFOA Water Line Extension Work Local traffic (including buses) WILL be accommodated.  Men and equipment will be in the roadway.  Please use Caution and Expect Delays.

Red Pine Road will be reduced to One-Lane Traffic for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

River Road to Orebed Road will be reduced to One-Lane Traffic for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

Riverside Drive will be reduced to One-Lane Traffic for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

Royal Street (North Benn) will be reduced to one-lane traffic for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

Scott Street will be CLOSED all week to through traffic while Highway crews continue to excavate, remove & replace sidewalks, curbing and water valves.  Men and equipment will be in the roadway.  Please use find Alternate Route.

Silk Road will be reduced to One-lane traffic for Paving Work through Aug 03rd, 2018.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

South Street from Crescent Blvd to Merson St will be reduced to One-Lane traffic through August 10th.  A private contractor will be working with the Water Department to replace a water line crossing in anticipation of the Route 7 State Paving project.  Men & equipment will be in the roadway.  Please use Caution and Expect Delays for the next 2 weeks.

Susan Taylor Lane & Asa Way (North Bennington) will be reduced to one-lane traffic for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

Vail Road will be reduced to one-lane traffic between Red Pine Rd and Silk Rd for Paving through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

Walloomsac Road will be OPEN but reduced to One-lane traffic through August 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

**William H. Morse Airport may be accessed by way of Dermody Road

Wilkie Way will be reduced to one-lane traffic for PFOA Water Line Extension Work through Aug 03rd, 2018.  Local traffic (including buses) WILL be accommodated.  Men and equipment will be on edge of the roadway.  Please use Caution and Expect Delays.

 

TOWNWIDE:

Highway Crews continue Roadside Mowing, sign replacements, crosswalk painting and road patching due to water digs around town.  Many roads may be reduced to One-lane.  Men and equipment will be in or on the edge of the roadway.  Please use Caution and Expect Delays.

 

STATE PROJECT:  Rte 7 North-South / Rte 9 East-West:

The Bennington Paving Project begins along Route 9 in the vicinity of the 4 Chimneys Inn and continues east for approximately 2 miles through downtown Bennington and ends at the state highway limits, near (Bakkerij Krijnen).  The Route 7 portion of the project begins near the Park Lawn Cemetery and continues north for approximately 1.5 miles to Veteran’s Memorial Drive (near the Chamber of Commerce).

Work to be performed includes cold planning of the existing pavement, surface preparation, paving with a leveling course and a wearing course, drainage, line striping and stop bar detection.  There will be temporary parking restrictions throughout the week of 7/30 within the active milling operation each day. As soon as parking can be safely re-opened, the contractor will do so.  Please take caution as men and equipment will be in the roadway.  Expect Delays.

 

Reminder:

Residents and Contractors – Please make sure all loads are covered when taking leaves and or brush to the transfer station.