Public Works Project List (June 20 – June 24, 2016)

Town of Bennington Project List

Week of June 20 – June 24, 2016

Highway Department

Monday –Friday Crews will be regrading driveways and lawns along the newly paved streets, Oakes Street, Rockwood Street, Crescent Blvd., Eastside Drive, Westside Drive and Transportation Drive, please use caution as highway personnel and equipment will be in the road.

  • A crew will be starting the sewer/stormwater /paving project on Corey Lane, residents will be allowed to enter and exit their residences with little delay.
  • A crew will be finishing pavement markings this week, use caution when entering the work zones.
  • Roadside mowing will take place all week, use caution when mowing equipment is in the road.

All Work will be dependent on weather conditions. Please use caution when entering a construction zone, men and equipment will be in the traveled portion of the road.

Notice:

Residents and Contractors – Please make sure all loads are covered when taking leaves and or brush to the transfer station.