Public Works Project List (June 8 – June 12, 2015)

Water Department

Tuesday through Friday-Water crews will be making water line repairs on Pleasant Street between Park and Main Street.  This work will require some interruption of water service; individual residents will be notified prior to interruption.  This work will also require road closure to through traffic.  Road Closed signs will be posted.

Wastewater

Monday through Thursday-Wastewater Crews will be making manhole repairs on Elm Street between Dewey and Monument Avenue.  This work may require one-lane traffic.  Watch for sign postings.

Highway Department

Monday through Friday – Highway Crews will be trimming trees and brush back off the Middle Pownal Road.

Highway Crews will be patching pot holes at numerous locations throughout town.

A crew will be ditching and doing shoulder work all week on South Stream Road, Crosswalk painting will be taking place throughout town.

Monday- Tuesday

Highway Crews will be cleaning debris under the bridge on East Main Street, between Branch St. and Burgess Road.

All above work will have lane closures and traffic control only, please use caution when entering a construction zone, men and equipment will be in the traveled lane.

Monday and Tuesday June 15 and 16, 2015 Houghton lane will be closed to through traffic, all transfer station traffic shall enter from Route 7 A, Highway Crews will be installing culverts on the East Road side.

All Work will be dependent on weather conditions.

Please use caution when entering a construction zone,

men and equipment will be in the traveled portion of the road.

 

Notice:

Residents and Contractors – Please make sure all loads are covered when taking leaves and or brush to the transfer station.