Roadwork July 20-24, 2020

Town of Bennington Project List

Week of July 20 – 24, 2020

 Please be Advised: The PFOA Water Line extension work continues. 

 Apple Hill Development (All Roads within): will be reduced to One-Lane Traffic while contractor continues paving roads within development.  Please use Caution as men & equipment will be in or on the edges of the roadway.  Expect Delays.

Burgess Rd (Center St to Main St): Reminder: this section of Burgess Rd has been milled and is still rough while waiting for paving.  Please use Caution and Expect Delays

Carpenter Ln: (Off North Branch St) will have lane restrictions while PFOA water main extension work continues.  Please use Caution and Expect Delays

Chapel Rd: will be reduced to One-Lane Traffic for the next several weeks as contractor crews begin setting up for the next phase of PFOA water line extension work.  Men and equipment will be on edges of the roadway.  Please use Caution and Expect Delays.

East Rd (Upper): North of Houghton Lane will be CLOSED for the next 2 weeks as a contractor crew continues PFOA water main extension work.  Men and equipment will be in the roadway.  Detours will be in place. Please schedule your time accordingly to account for these detours or find an alternate route.

Furnace Brook Rd: (at North Branch St) will have lane restrictions while PFOA water main extension work continues.  Please use Caution and Expect Delays

Gage St: (Bradford St to Grove St): Tuesday & Wednesday will be CLOSED as a contractor makes a new water connection for the Rec Ctr expansion project.  Men and equipment will be in the roadway.  Detours will be in place. Please schedule your time accordingly to account for these detours or find an alternate route.

Kocher Drive: between Aldi’s and Performance Dr continues to have lane restrictions while a contractor continues work on the Pedestrian Sidewalk Extension project.  Men and equipment will be in or on the edge of the roadway.  Please use Caution and Expect Delays.

North Branch St: will be reduced to One-Lane Traffic while the crews prepare for paving.  Reminder: this entire road has been milled and is still rough while waiting for paving.  Please use Caution and Expect Delays

Polygraphic Ln (N.Benn): will be reduced to One-Lane Traffic for the next 3 weeks while a Sewer Crew works on the Sewer Main Replacement project.  Men and equipment will be in the roadway.  Please use Caution and Expect Delays.

Willow Road: will continue to be reduced to One-Lane Traffic all week for PFOA Water Line Extension Work.  Men and equipment will be in or on edges of the roadway.  Please use Caution and Expect Delays.

TOWNWIDE:

A private contractor will continue roadside mowing throughout town.  Please use caution when approaching these areas and expect delays.

Highway crews will be repairing and replacing street signs throughout town.  Men and equipment will be roadside.  Please use caution when approaching these areas.

Sewer crews will be repairing manholes in various areas.  Please use caution when approaching these areas.

All Work will be dependent on weather conditions.  Please use caution when entering a construction zone, men and equipment will be in the traveled portion of the road.

 

REMINDER – Summer :

Please DO NOT rake or blow leaves into Town streets or Highways as this clogs storm drains and creates flooding and driving hazards for the entire community.

Residents and Contractors – Please make sure ALL LOADS ARE COVERED when taking leaves and or brush to the Transfer Station.