Division Street remains Closed to through traffic all week. Local traffic WILL be accommodated. Highway Crews will be replacing storm drains in preparation for paving. Men and equipment will be in the roadway. Please find alternate route.

Grove Street –will be CLOSED from 7:30am to 3pm to through traffic all week, local traffic WILL be accommodated for water line repair. Please use caution when approaching as men and equipment will be in the roadway.

Park Street – will be CLOSED to through traffic between Gage St & Scott St as Highway & Sewer will be replacing storm drainage and manhole rehabilitation. Local Traffic will be accommodated. Please use caution when approaching as men and equipment will be in the roadway.

Townwide Work:

Roadside mowing, tree trimming and weeding also will continue in numerous areas in Bennington. Please use caution when approaching these areas and leave plenty of room for the tractor and men or equipment on side of the road.

Reminder:

Please DO NOT rake or blow grass and/or leaves into Town streets or Highways as these clogs storm drains and creates flooding and driving hazards for the entire community.

 