Town of Bennington Public Works Project List – (September 8 – September 11, 2015)

Town of Bennington Project List

Week of September 8 – 11, 2015

Water Department

Tuesday-Water Crews will be making a water main repair on Tinkham West near the dead end portion of the street. Water will be turned off between 8am and 1pm. Customer that will be affected by this shut down will be notified prior to the shut down

Wednesday & Thursday-Water Crews will be making water line repairs on East Main Street between Rockwood Street and Burgess Road. This work will require that water be shut down between 8am-1pm during this process. Those residents and businesses that will be affected will be notified prior to the shut down. One-Lane traffic will be necessary and traffic control will be provided. Motorists should expect delays and local traffic might want to seek alternate routes of travel.

Highway Department

Tuesday-Friday-Highway Crews will be starting the River Bank stabilizing project on Kocher Drive between Performance Drive and Park Street, a temporary lane change will take place in order to keep both East and West bound traffic moving. Please use caution when entering this work area, road surfaces will be changing.

A Highway Crew will start the Pleasant Street curb and sidewalk project, through traffic will not be permitted to travel Pleasant Street between Main Street and Park Street.

Roadside mowing will take place, please use caution when approaching these worksites.

 All Work will be dependent on weather conditions.

Please use caution when entering a construction zone,

men and equipment will be in the traveled portion of the road.

Notice: Residents and Contractors – Please make sure all loads are covered when taking leaves and or brush to the transfer station.