Town of Bennington Project List
Week of July 11 – July 15, 2016
Highway Department
Monday-Friday
Morgan Street will be closed to through traffic. a highway crew will be building a retaining wall along the Village Cemetery.
A highway crew will be installing storm drainage along Corey Lane, residents will be able to enter and exit.
A private contractor will be replacing the roof on the henry Bridge, the bridge will be closed to all traffic.
Roadside mowing will take place all week.
Tuesday-Friday
A private contractor will be paving at the various locations in the following order: Sunset Drive, Gore Road, Burgess Road, and Barney Road.
All Work will be dependent on weather conditions.
Please use caution when entering a construction zone, men and equipment will be in the traveled portion of the road.
Notice: Residents and Contractors – Please make sure all loads are covered when taking leaves and or brush to the transfer station.